NOVA estimated that repairs to a flange assembly leak on its NorthLateral (see Daily GPI, May 17), whichstarted Wednesday, would take 24-36 hours to complete. Some receiptsupstream of Dusty Lake Compressor Station are being curtailed by thework.

PG&E Gas Transmission-Northwest expected to complete work onits A-Line Wednesday night and said Kingsgate capacity would rise from2,050 MMcf/d to 2,280 MMcf/d for today’s gas day, limited by thecontinuing outage of Unit 5-C. With the A-Line back in service,capacity for deliveries into Northwest at Spokane, WA, will return tonormal (see Daily GPI, May 17), PG&EGT-NW said.

Tennessee restored all services at 14 meters Wednesday followingearly completion of rehab work on the Kinder-Natchitoches Line inwestern Louisiana.

©Copyright 1999 Intelligence Press Inc. All rights reserved. Thepreceding news report may not be republished or redistributed, inwhole or in part, in any form, without prior written consent ofIntelligence Press, Inc.