Nova Gas Transmission Ltd. (NGTL) is days away from ramping up natural gas flows as operators work to bring fully online an extension of the 15,305-mile Canadian pipeline.

Aeco

TC Energy Corp.’s Minh Badau, commercial operations spokesperson, told NGI that the pipeline operator is in a “day-to-day assessment” of when it can safely bring online the final component of the North Corridor Expansion Project.

In a presentation Thursday, TC said a suction valve at the Hidden Lake North Compressor Station was found to be leaking and resulted in a 12-day delay. The North Corridor project includes the construction of a 30 MW unit at the compressor station.

In addition, several items were identified that need to be addressed before the unit is placed into service, according to TC. The...