At the start of Wednesday’s gas day MRT will lift the System Protection Warning placed into effect Nov. 23.

CenterPoint has canceled limits on storage transactions that were implemented in September and said it is no longer assessing Excess Contract Quantities penalties against pool managers who incur new long imbalances (see Daily GPI, Oct. 6).

South Mainline capacity will be reduced by about 350 MMcf/d on Dec. 5 when Line 1100 is removed from service between the Eunice and Pecos River Stations for 24 hours to perform maintenance and inspection of anomalies, El Paso said.

Sea Robin Pipeline has once again postponed the return to service for two meters at the South Marsh Island 128 platform that had suffered hurricane damage last year (see Daily GPI, Oct. 18). Jan. 1, 2007 is now the anticipated date, Sea Robin said.

Ongoing scheduled maintenance on the Clarence (LA) Compressor Station’s Unit #1 has been extended through Dec. 5 due to a contractor’s scheduling issues, Gulf South said Tuesday. Capacity through the station could be reduced by as much as 100,000 Dth/d during this work.

As a result of terminating contracts, Questar is taking bids through Dec. 19 on a variety of firm capacity packages that will become available beginning March 1, 2007. See the bulletin board for details.

©Copyright 2006Intelligence Press Inc. All rights reserved. The preceding news reportmay not be republished or redistributed, in whole or in part, in anyform, without prior written consent of Intelligence Press, Inc.