PG&E Gas Transmission-Northwest reported completing hydrotesting of its A-Line ahead of schedule. The project’s end restoredcapacity to best-efforts levels of 2,620 MMcf/d at Kingsgate and1,930 MMcf/d at Station 14 Friday.

Empress/McNeill Border delivery capacity will be limited toabout 8,640 MMcf/d today through Thursday during an outage of thePaul Lake Compressor Station, NOVA said. The constraint resultsfrom less flow being able to move down the North Lateral during thePaul Lake outage and while work on Princess B Unit #7 continues,the pipeline added.