PG&E Gas Transmission-Northwest reported completing hydro testing of its A-Line ahead of schedule. The project's end restored capacity to best-efforts levels of 2,620 MMcf/d at Kingsgate and 1,930 MMcf/d at Station 14 Friday.

Empress/McNeill Border delivery capacity will be limited to about 8,640 MMcf/d today through Thursday during an outage of the Paul Lake Compressor Station, NOVA said. The constraint results from less flow being able to move down the North Lateral during the Paul Lake outage and while work on Princess B Unit #7 continues, the pipeline added.